June 26, library packing July 4, Researched fresco July 10, Library packing
Jujy 11, Hidden fresco openning Oncovered fresco "Christening" July 12, Taking samples for tests
August 15, Library relocation August 17, Cracks open August 22, Injections to strengthen walls
August 22, Damaged brick replacement August 30, facades injections preparation September 1, Damaged brick removed
September 19, Facades walls strengtheing September 19, Old bookshelves removal Septembe 20, Ceiling strengthening
September 21, found books behind shelves September 21, Damaged brick replaced October 2, closing lower walls
Oct.10, Injected ceiling Oct.06, replacing damaged brick Oct.06 preparing facade works
Oct.18 Facade Strength Oct 18, Injected ceiling Oct.18 Protected fresco
Oct.19 Facades Oct.27 State of wall in Congregation Hall Oct.30, Preparations to hydroizolation
Nov.3, Strengthening Congregation Hall walls , Nov.10, Coal delivery canale Nov.11, 19 century oven discovered
Nov.28, Arches reinforcement, Dec.12, Reinforced doorway in Congregation hall
Restoration and project documents were done with state funding, while relocation of library and other departments with university funding